Construction Progress and Campus Updates
Current information regarding parking, entrances, and site activity during campus improvements. Last updated: June 19, 2026
🟢 Clinic Open
🟡 Driveway Access Changes
🟢 Main Entrance Open
Temporary Fencing Adjustments – June 22
Starting on Monday, June 22, crews will be installing additional fencing in the areas highlighted on the map.
This fencing will support upcoming curb, gutter, and sidewalk improvements and help keep everyone safe as activity increases.
Because of this, access to the west parking lot and portions of the north dirt driveway will be temporarily affected. You may also notice new signage and changes to traffic flow in these areas.
If you're visiting campus, please follow posted signs and allow yourself a little extra time to get where you're going.
As always, clinic operations will remain open. Thank you for your patience and support as work continues.
Recent Updates:
June 10 — Clearing and Grubbing
May 15 — Fencing Installation
May 13 — Sequoia tree removal completed
April 17 — Groundbreaking Ceremony Held
For questions or concerns, please contact CTHP at (707) 485‑5115.